Construction Schedule

Dec. 2004 ~ Sept. 2006: Building construction
Jun. 2005 ~ Mar. 2008: Accelerator equipment and components manufacture and      assembly
Dec. 2005 ~ Dec. 2008: Beamline construction and assembly
Apr. 2007 ~ Jul. 2007: Linac commissioning
Oct. 2007 ~ Mar. 2008: Booster commissioning
Apr. 2008 ~ Oct. 2008: Storage ring commissioning
Nov. 2008 ~ Mar. 2009: ID Beamline commissioning
Apr. 2009: The SSRF operation begins